Industry: Mining
The Challenge
A contractor working for one of Australia’s largest mining companies required a compressed air solution that could be deployed quickly and operate reliably in a mining environment. The project demanded multiple compressors with integrated air treatment, minimal on-site installation time, and complete confidence that the equipment would perform as expected upon arrival. With tight schedules and limited tolerance for commissioning delays, the system needed to be fully site-ready before delivery.
The Solution
Pneumatic Engineering designed and supplied a custom dual compressor package tailored to the project requirements. The solution included an ELGi EG37kW compressor paired with an EGRD300 refrigeration dryer and air receiver, alongside an ELGi EG11kW compressor with an EGRD200 dryer and air receiver. Both systems were mounted on custom-engineered skids and configured with single point electrical connections to simplify installation and reduce on-site electrical work.
Prior to dispatch, all equipment underwent full factory acceptance testing (FAT) with site inspectors present. This ensured performance, compliance, and integration were verified well before the equipment reached site.

Results
The completed package delivered a fast, straightforward installation and a reliable compressed air supply from day one. By FAT-testing the systems prior to delivery, Pneumatic Engineering eliminated commissioning risks and provided the client with confidence in system performance. This project highlights Pneumatic Engineering’s capability to deliver custom, fully tested compressed air packages for critical mining applications.

Got a unique problem? We’ve got a unique solution. Get in touch today.